CASE STUDIES

St Oswald’s School, York

Client: Sewell’s
Location: York
Project Value: £25,000 (approx.)
Project Duration: 6 weeks

Project Description:
New extension to an existing school building.

Scope of Works:

  • Dot and dab to blockwork walls 
  • Plastering 
  • Tape and joint finishes 
  • Suspended ceilings 
  • MF ceiling

Outcome:
The works were completed within the 6-week programme and coordinated successfully alongside other trades in a live school environment. Finishes were delivered to a high standard and the project was handed over on time, meeting the client’s requirements.

I wanted to take a moment to thank you and your team for all the hard work and commitment you’ve shown throughout this project.

Your collective effort really made a difference, and it showed in the final result.

The client was genuinely delighted with the build, and it’s thanks to you and your team’s dedication that we were able to successfully hand the project over on Wednesday.

I truly appreciate the time and energy put into this scheme. Please pass on my thanks to all the operational team members who put in the graft and helped make the project what it is today.

I look forward to working with you again on future projects.

Site Manager feedback

Yorkshire Cancer Research Offices

Client: Londstone Projects
Location: Hull
Project Value: £70,000
Project Duration: Approximately 2 months

Project Description:
Office fit-out within an existing building.

Scope of Works:

  • Internal partitions
  • Bulkheads 
  • Tape and joint finishes 
  • Suspended ceilings

Outcome:
The project was delivered to programme with minimal disruption to the existing building. Our team maintained a high quality of finish throughout, enabling the space to be handed over ready for occupation. The client was pleased with both the workmanship and overall delivery.

Quick note to advise completion was accepted today by the client’s team who were universally over the moon with the quality and journey they have been on with us all.

I have to say I haven’t been to many hand overs feeling as confident as I felt today – we hit every single metric we could have on this one with an on time, high quality, on budget delivery and a client who has enjoyed the process of working with us all so handing over felt like a given which isn’t something I can always say!

Client feedback - Director

Marble Hall School

Client: Integra Building
Location: Stockport
Project Value: £22,000

Project Description:
Ceiling works within a school environment.

Scope of Works:

  • Suspended ceilings

Outcome:
The suspended ceiling installation was completed efficiently and within the agreed timescales. Works were carried out safely and to specification, resulting in a smooth handover and a satisfied client.